Mount Fernie Provincial Park Project

Mount Fernie Provincial Park Project is now underway. Please see below for the proposed timeline as well as the attached map for the concept plan.  

Now until December 20th, 2018:

  • Tree removal for the new campsites and the new parking lot
  • The new parking lot and the Gorby parking lot expansion are complete with base material installed. Some organics still to be taken away from the Gorby site.
  • Road base will be laid down on the new road through the campground.
  • Base material will be laid down for each of the new campsites one at a time.

Spring 2019 (as soon as weather conditions permit):

  • Resume works to complete construction of campsites and parking lots. Lay a base material for any sites that did not receive it last fall and then start laying down the final crush layer, fire rings and furniture.
  • Remove and rehabilitate entrance parking lot.
  • Upgrade Mt. Fernie Park Road including construction of hiking trails on road sides and safety features. 

The goal is to have the project completed by November 2019.